Overview

Don’t let the acreage fool you, at 350,000 CY of cut-to-fill across 230 acres, Morgnec was one of AG-CON’s most earthwork intensive solar projects to date. AG-CON cleared the hilly terrain, managed significant grading across the site, and installed 9 sediment basins to prepare the ground for the solar facility. 

Highlights: 

  • 230 acres cleared and graded
  • 45 MW solar facility
  • 350,000 CY cut-to-fill
  • 9 sediment basins installed