Beauregard Compressor Station

SERVICE
Drainage Structures, Grading/Excavation, Soil Stabilization
MARKET
Oil & Gas
STATE
LA
Overview

A 53-acre compressor station site demanded heavy earthwork and precise drainage infrastructure to meet the exacting standards of the oil and gas industry. AG-CON moved 75,000 CY of cut-to-fill, placed 60,000 tons of aggregate, and installed 3,000 linear feet of stormwater infrastructure — building a stable, well-drained foundation for a critical energy facility. 

Highlights: 

  • 53-acre site
  • 75,000 CY cut-to-fill
  • 60,000 tons of aggregate placed
  • 3,000 LF of stormwater infrastructure installed